1. Install a fused disconnect device having sufficient interrupting capacity to clear the maximum fault current capability of the power supply Decanter Centrifuge.
2. Remove the plug from hole at top of the electrical junction box, install appropriate feed-through into the hole, and attach rigid conduit. Pass three-phase cable through the conduit and into the shale shaker.
3. Connect three-phase power leads to the terminals at the top of the starter block as shown in
THREE-WAY VALVE CONTROL ARM
For protection during shipment, the control arm is not connected to the valve. The control arm is
restrained by a tie wrap , which must be removed to permit connection to the
valve. Before operating the degasser, attach the control arm to the three-way valve as follows:
1. Remove the 5/16-inch bolt and nut from the control clevis at the top of the valve.
2. Remove and discard the plastic tie wrap retaining the valve control arm.
3. Swing notched end of the control arm down into control clevis, and reinstall nut and bolt.
4. Check for and remove any obstruction of valve’s atmospheric vent.